Research Progress
Home > Research > Research Progress
Bituminous concrete-faced anti-seepage technology for pumped-storage power plant and its application in Baoquan project
Time: 2016-06-06 | Hits:

Bituminous concrete-faced anti-seepage technology for pumped-storage power plant and its application in Baoquan project has won the second prize of 2015 Henan Provincial Award for Science and Technology Progress.

It is developed by IWHR based on advanced German technology, and has been customized and improved for the past two decades and successfully applied in other pumped-storage power plants such as Tianhuangping and Hohhot.


Bituminous concrete-faced anti-seepage construction for Baoquan pumped-storage power plant

  


Read more:
 ·IWHR-developed waterstop structures applied to Banjianhe Reservoir
 ·IWHR wins first prize of 2016 Science and Technology Progress Award for Power Development
 ·BITC’s H9000 computer monitoring system withstands full load rejection test in pumped-storage power plant
 ·Stabilizing slurry using plaster used for the first time in subway construction for anti-seepage and reinforcement
 ·Impervious bituminous concrete facing applied for 2022 Winter Olympics

     