IWHR effectively controls water bursts in diversion tunnel
Time: 2016-07-13 | Hits:

IWHR successfully controlled the water bursts in the diversion tunnel of Daping Hydropower Station that had been constructed by drilling and blasting, causing spring No. 1 to dry up for over half a year and spring No. 2 to drop in water level and water quality.

Difficulties faced including the well-developed cracks of fault in this region, large flow, high pressure, and short distance between the bursts and the springs. By adopting low-temperature bitumen, fast-hardening paste slurry and mold bags, major seepage passages in the tunnel were successfully stopped. After grouting, water started oozing out of spring No. 1 while water level and quality of spring No. 2 were restored, guaranteeing water demand of the local community.

Two years after the construction, no new water bursts occur in the treated section of the tunnel, nor does water decrease in spring No. 1 and No. 2, proving a reliable quality of grouting.

Read more:
 ·Stabilizing slurry using plaster used for the first time in subway construction for anti-seepage and reinforcement
 ·Application of Plaster Grouting in Seepage Control and Water-Stop Engineering of Coffer Dam for Bridge Piers
 ·Deze Reservoir Safety Monitoring for Water Diversion Project from Niulan River to Dianchi Lake
 ·IWHR Updates Governor of Baozishi Hydropower Station
 ·IWHR Upgrades Governors for Honghua Hydropower Station in Guangxi

     

A-1 Fuxing Road,Haidian District,100038 Beijing; +86-10-68781650 (office); +86-10-68412316 (fax); dic@iwhr.com

Produced By CMS 网站群内容管理系统 publishdate:2023/10/07 13:13:33